The 7-step LOTO standard operating procedure cannot be omitted in any step.
Based on the GB/T 33579-2017 standard and the on-site practical experience, we have compiled a standardized 7-step LOTO procedure. Each step has clear operation requirements and precautions,
and it can be directly followed without any additional disassembly.
Step 1: Identify risks, ensure everyone is informed Before starting the
operation, all relevant personnel must be notified in advance -
including equipment operators, control room staff, team leaders, and
personnel from adjacent positions. Clearly inform them about "which
equipment, which part, at what time, and what kind of maintenance is
being carried out" to ensure that irrelevant personnel are aware that
the equipment is about to enter the maintenance state and avoid
accidental operations. At the same time, identify all dangerous energy
sources of the equipment comprehensively, such as the main power supply
of electrical equipment, branch power supplies; hydraulic system valves;
pneumatic system valves; steam pipes' steam valves; and residual energy
of the equipment (such as unreleased pressure, suspended components'
gravity), and register them one by one to ensure there are no omissions. Key points: Only notifying the operators, ignoring the
control room staff, led to the control room mistakenly triggering the
equipment startup; missing residual energy, such as the hydraulic system
not being depressurized, resulting in unexpected energy release during
subsequent operations.
Step 2: Standardize shutdown, operate according to regulations It is strictly
prohibited to perform emergency shutdowns (unless there is an emergency
danger). The equipment must be shut down gradually according to its
established shutdown procedures: first, stop the equipment operation,
close the relevant operation switches, wait for the equipment to
completely stop running (such as the motor stopping, mechanical
components remaining stationary), and then proceed to the next step. For example: In a workshop for centrifugal pump maintenance, the correct approach
is: first, close the outlet valve → stop the pump operation → close the
inlet valve, wait for the pump body to completely stop running, rather
than directly pulling the switch to cut off the power supply, to avoid
damage to the pump body or accidental release of residual pressure.
Step 3: Physical isolation, completely cut off energy This is the core step of
LOTO - for each identified dangerous energy source, take physical
isolation measures to ensure that the energy cannot be transmitted to
the operation area. Common isolation methods include: electrical system:
disconnect the main power switch, branch power switches, and remove the
power plug (for portable equipment); hydraulic/air pressure system:
close hydraulic valves, airway valves, and if necessary, install blind
plates (to prevent valve leakage); steam/liquid pipeline: close valves,
install blind plates, release residual media in the pipeline; mechanical
components: use pins, barriers to fix suspended components (such as
forks, mechanical arms), to prevent gravity from causing a fall. Key points: Only closing the operation panel switch, without disconnecting the main
power supply; not installing blind plates after closing the valves,
resulting in valve leakage and unexpected energy release.
Step 4: Lockout tagout, clarify responsibilities After isolation, immediately
lock and tag each isolation point (such as power switches, valves), the
core of this step is "one person one lock, clear responsibilities".
Step 5: Release residual energy, eliminate hazards After physical isolation,
there may still be residual energy inside the equipment (such as
residual electrical energy, hydraulic pressure, air pressure, residual
heat), it must be completely released and blocked to ensure the
equipment is in a "zero energy state": electrical equipment: after
closing the switch, press the equipment start button to verify no
response, and check the voltage reading is zero; hydraulic/air pressure
system: open the pressure relief valve to release the residual pressure
in the system, wait for the pressure gauge to show zero, then close the
pressure relief valve; high-temperature equipment: wait for the
equipment to cool down to a safe temperature to avoid burns; mechanical
components: manually check the suspended components to confirm they are
firmly fixed and there is no risk of falling. Key points: Skipping the residual energy release step, thinking "power off is
fine", resulting in unexpected release of residual energy, causing
casualties.
Step 6: Isolation verification, confirm safety This is the most easily
overlooked but the most crucial step - after releasing the residual
energy, it must be re-verified to ensure the isolation is effective and
the equipment cannot be started. Correct approach: The
operator personally attempts to start the equipment (such as pressing
the start button, turning the operation lever, opening the valve),
confirm that the equipment has no response; at the same time, check the
locks, tags at each isolation point, whether the residual energy release
is complete, whether the pressure gauge, voltage reading are zero, only
when all are confirmed without error, can start the maintenance
operation. Key reminder: During the verification
process, it is essential to ensure that no other personnel are present
in the work area to avoid accidental activation (if there is residual
energy) during the verification, which could cause injury; after the
verification is completed, all controllers must be reset to ensure that
the subsequent equipment returns to normal operation.
Step 7: Release and restore, after the standardized unlocking and maintenance
are completed, do not unlock randomly; follow the following procedures
without any mistakes: Clean up the site: Check the work area to ensure
that all tools, parts have been retrieved, no debris is left, the
equipment components are installed properly, and the protective devices
have been restored; Personnel count: Confirm that all workers have
evacuated the work area and no personnel are left behind; Notify
relevant personnel: Inform the operator, the central control personnel,
and the team leader that "The maintenance is completed and the unlocking
and restoration will be carried out shortly"; Unlocking principle:
Strictly follow the "Who locks, who unlocks" principle; Personal locks
should be removed by the individual themselves; It is strictly
prohibited for others to replace; For collective locks, all workers must
remove their personal locks before the operation supervisor can unlock
uniformly; Restore the equipment: Remove the isolation tools (such as
blind plates, pins), restore the valves and switches to the normal
position, then conduct equipment trial operation to confirm that the
equipment operates normally without abnormal noises, leaks, etc., and
this is considered the completion of the entire LOTO process.
Supplementary: If the work is not completed, the workers need to
temporarily leave; It is necessary for the supervisor or the replacement
personnel to re-lock and label before the original workers can remove
their locks; During shift handover, the person handing over cannot
directly remove the locks; The person taking over must lock and label
before the person taking over can remove their own locks; If the
equipment stops running for more than 8 hours, the supervisor is
responsible for lockout tagout.